Enquire now

Discuss your project requirements

So tell us...
What project is keeping you up at night?

ICON provides excellent engineering solutions. Complete this form and we'll get a problem solver on the case for you right away.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Shell Oil UK

Shell Skiff Field Development: Platform Installation by Jackup Rig

ICON Engineering was commissioned by Shell to provide assistance with the installation of the Skiff wellhead platform in the Southern North Sea. The platform was installed by a jackup drilling rig.

Installing Shell's Skiff wellhead platform, North Sea

Installing Shell's Skiff wellhead platform, North Sea

 

This was the first platform to be installed by this means in the UK sector of the North Sea. The installed cost was a fraction of that required using conventional methods.

The project won the British Government Construction Industry Civil Engineering Award for 2000 in recognition of the novel design and installation method which challenged traditional practices.

ICON's involvement at the client level allowed Shell to take advantage of our site experience with this style of installation. ICON's scope included review of: installation methodology, critical success factors, schedule, key deliverable's for contractors, installation criteria and risk (safety and schedule) reduction. ICON also assisted with management of key interfaces and contractors and attended offshore during the installation.

Jacket Installation

The platform jacket and topsides were transported to site on a small flat top barge. Transporting the Jacket vertically eliminated the need for upending. The barge was moored to the rig legs. Four 30 inch skirt piles were preloaded into the pile sleeves to reduce rig time during pile make-up.

Shell Skiff jacket lifting.jpg

Lifting off the Skiff jacket
 

 

The platform mudmat is minimal as the structure is stabilised by the rig during piling. After lift-off and placement the piles were installed using a drill-drive procedure which limits formation damage and guarantees penetration.

Topsides Installation

Topsides installation occurred after piling. Drilling commenced immediately after the topsides installation.

Installing Skiff.jpg

Lowering the topsides onto the Skiff jacket

 
Platform Data
Waterdepth 30m
Jacket Lift Weight 450t (incl pre-loaded piles)
Topside Weight 200t
Well Slots 6
Legs 4 vertical
Piles 4 vertical
return_to_top
© 2024 ICON Engineering
Powered by Kinetic.