Enquire now

Discuss your project requirements

So tell us...
What project is keeping you up at night?

ICON provides excellent engineering solutions. Complete this form and we'll get a problem solver on the case for you right away.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

WAPET (now Chevron)

WAPET Roller Skate Joint Development Project, North West Self, Western Australia

ICON founders, Garrick Aberle and David Field were respectively the Project Manager and Designer / Senior Installation Engineer for this project. The development consists of 4 monopod platforms, two subsea pipelines and shore based oil separation and gas sales conditioning facilities.

Chevron_Roller&Skate (Australia NW Shelf).JPG

The Roller Skate development

 

The Roller and Skate oil fields are located in the Carnarvon Basin offshore Western Australia. The combined field development consists of 4 monopod platforms  - Roller A, B, C and Skate, and two pipelines. One line carries three phase product to Thevenard Island whilst the other carries gas from Thevenard to the mainland. These pipelines were 26 and 36 km long respectively and were constructed using the bottom tow method. At the time, this was one of the longest pipelines in the world constructed in this manner.

Substructure Installation by Jackup Rig

The 4 x 135 tonne topsides and 4 x 140 tonne sub-structures were fabricated in the Perth metropolitan area. The substructures were transported from Perth to site together on a barge and installed using the jackup drilling rig "Hakuryu 9" in a single installation phase.

The substructure installation phase occurred well in advance of the topsides installation. This allowed development drilling to occur parallel with topsides fabrication, allowing a longer duration and reducing the impact of any unforeseen delays in topsides fabrication.

Topsides Installation

The four topsides were road transported from Perth to Onslow where they were temporarily stored. They were then loaded out onto a small barge and installed with a jackup rig in one day each to match the development drilling program and rig movements.

Detailed installation procedures aimed at reducing construction risk allowed each complete platform to be installed in an average of 6 days.

All platform transportation, installation and commissioning work was executed by an in-house WAPET team led by the ICON Directors.

Pipelines 

The 508mm oil pipeline and the 168mm gas pipeline were constructed using the bottom tow method. An onshore stringing site, some 4.5 kms long, was set up at Tubridgi, approximately 10km from the Roller field.

Gas Treatment Plant

A gas treatment and compression plant capable of handling up to 20mmscfd of gas was constructed adjacent to the existing oil treatment facilities on Thevenard Island.

Other Works

The project also included the installation of a new turbine generator, a slug catcher and separator vessel, island road works and a 100 personnel camp.

return_to_top
© 2024 ICON Engineering
Powered by Kinetic.