Enquire now

Discuss your project requirements

So tell us...
What project is keeping you up at night?

ICON provides excellent engineering solutions. Complete this form and we'll get a problem solver on the case for you right away.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Apache Energy Corporation

Apache Linda Field Development Platform Installation

Apache Energy engaged ICON Engineering to undertake the installation of the Linda Platform offshore Western Australia. The 355 tonne jacket was lifted horizontally using the jackup rig Ensco 56. The jacket was upended and lowered to the seabed using ICON’s proprietary lifting sub arrangement. Installation of the 50m long jacket and topsides took place in February 2004. 

Installing the Linda platform.jpg

Installing the Linda platform

 

The jacket and topsides were fabricated in Kwinana and then assembled at the newly built Australian Marine Complex (AMC) facility at Jervoise Bay, Perth. The three overhead cranes available allowed the lift rigging to be pre‑installed on the jacket before loadout.

The jacket and topsides were then transported to Dampier by HLV (topsides located within the hull) and then loaded onto a flat top barge ready for tow to site.

The 355 tonne jacket was lifted horizontally using the F&G L780 Mod II Jackup rig “Ensco 56” in approximately 34m of water.

Linda install6.JPG

The jacket was upended and lowered to the seabed using ICON’s proprietary lifting sub arrangement.

Linda install2.JPG

A theodolite was used to ensure the jacket was correctly orientated and within the drillable area for piling.

The installation of drilled and grouted piles then followed. A 1380mm diameter reverse circulation drilling assembly was used to drill the battered holes. Piles were mechanically connected and run through ICON’s custom designed rotary table. Grout then secured the piles firmly into the seabed and prepared the jacket for the impact of Cyclone Monty that occurred soon after installation.

The installation of topsides was done by extending the rig cantilever beyond the jacket, picking up the topsides and skidding back under load to set the topsides onto the jacket for weld out.

The Linda Platform Installation is yet another successful project utilising a jackup rig to install the structure.

Linda install1.JPG

 

Platform Data

  • Water depth                 34 m

  • Jacket Lift Weight        355 t

  • Topsides Weight          135 t

  • Legs/ Wells                  3 vertical/ 6 wells

  • Piles                              3 x 1219mm diam. battered

return_to_top
© 2024 ICON Engineering
Powered by Kinetic.