Enquire now

Discuss your project requirements

So tell us...
What project is keeping you up at night?

ICON provides excellent engineering solutions. Complete this form and we'll get a problem solver on the case for you right away.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Apache Energy Corporation

Apache Double Island Project: "Minnowpod" Wellhead Platform Design & Installation, Western Australia

As part of its ongoing quest to develop previously uncommercial fields, Apache Energy, in conjunction with ICON, developed the “Minnowpod” concept. This monopod substructure is used as the surface conductor on shallow water exploration wells which have a high probability of success.

ICON carried out the design, fabrication and installation, due to extensive experience with minimal facilities platforms offshore. 

installing the Double Island topsides.jpg

Installing the Double Island topsides structure

Double Island oil field was discovered and developed in 2002. It lies between Varanus Island and Barrow Island off NW Australia. The water depth is approximately 6m LAT

The Minnowpod Wellhead Platform concept

As part of its ongoing quest to develop previously uncommercial fields, Apache, in conjunction with ICON, developed the "Minnowpod" concept based around a strengthened 30" conductor with mechanical connectors. This monopod substructure is used as the surface conductor on shallow water exploration wells which have a high probability of success.

Double Island during construction.jpg

The “Sirius” self-elevating platform located alongside the Double Island platform during installation

 

If the well proves commercial, a completion is run prior to the rig departing. Appropriate topsides are then designed and installed on the monopod later to allow production to commence. If the well is unsuccessful, the monopod is cut off at the mudline and recovered for re-use. Only the section below the seabed is expended.

The Double Island field is one of a number of fields known as the "String of Pearls" located within 13km of Varanus Island. The Minnowpod concept has been employed successfully on a number of the platforms on these fields.

ICON was engaged to undertake the design, fabrication and installation due to our extensive experience with minimal facilities platforms as well as our ability to execute the offshore component of the work in a fast timeframe.

The key requirements of the project were:

  • All work to be performed safely

  • Minimise capital costs

  • Minimise complexity of the structure

  • Undertake the work as quickly as possible

ICON worked closely with Apache to achieve these common goals.

Fast Track - completion in 3 months

Design, fabrication and offshore installation of the topsides, access ladders, risers and topsides piping were completed in 3 months due to constraints on availability of the construction jackup. This time scale also enforced the achievement of the other project objectives.

Use of construction jackup

Apache were able to capitalise on ICON’s recent experience with the "Sirius" self-elevating work jackup. This jackup was designed for drill and blast dredging operations. ICON had previously utilised it for conducting a coiled tubing workover on monopods in a nearby field for another operator and had developed specific operating procedures for it to work under a Safety Case environment. It was a low cost solution which allowed the work to be undertaken with minimal downtime.

Key features of the Minnowpod project include:

  • Structures designed with clamped connections so no field welding was required on site.

  • Minimal load on the conductor.

Lifting the Double Island topside structure onto the caisson.jpg

Lifting the Double Island topsides structure onto the caisson from a self-elevating work jackup rig.
return_to_top
© 2024 ICON Engineering
Powered by Kinetic.