IPC Malaysia
IPC Malaysia PM-3 Phase 1 Project: Bunga Kekwa A Wellhead Platform Topsides Installation, offshore Malaysia / Vietnam
ICON Engineering was commissioned to install the 220 tonne topsides using the Jackup Rig "Trident 17" operated by Sedco Forex and to coordinate the interfaces between the Jackup operator, IPC drilling department, IPC Project Group and topsides fabricator and FPSO/flowline installation contractor.
The complete topsides installation was carried out in a single day.
The Bunga Kekwa A Platform, Block PM3, between Vietnam and Malaysia.
The platform is operated by IPC Malaysia Ltd. Other participants are Petronas Carigali Sdn Bhd, Sands Petroleum AB and Petrovietnam Exploration and Production. The platform produced first oil on 30th July 1997 to an FPSO nearby via a flexible flowline.
ICON carried out the engineering in Perth and mobilised teams to Kuala Lumpur, the loadout site in Pasir Gudang near Johor Bahru, and to Sedco's Jackup Rig “Trident 17” for the construction phase. The water depth at the BK-A location is 56 m. The platform was designed by Ranhill Worley.
The option to use the jackup rig was chosen because it was significantly cheaper than using a derrick barge and because it offered the flexibility of being able to install the substructure and commence development drilling three months before the topsides was completed.
Topsides Loadout
The structure was fabricated by Sime Sembawang Engineering Malaysia and loaded out by sheer leg crane at Pasir Gudang. ICON engineered the loadout lift rigging and supervised the preparation of the topsides for offshore installation.
Marine Transportation
ICON prepared all seafastening designs and supervised the fitout of the barge with the necessary tow and mooring equipment. All naval architecture and design work for the loadout, tow and installation was the responsibility of ICON. The ICON onshore team ensured a timely sailaway to avoid the possibility of any rig delays. The topsides were carefully prepared with installation and hookup equipment to ensure the fastest possible offshore installation and hookup time. Topsides positioning on the barge was critical to suit the tight lift clearances using the jackup rig.
The Bunga Kekwa topsides during loadout
Topsides Installation
As the onshore ICON team prepared the topsides another ICON team simultaneously positioned the rig and made preparations for the topsides lift. Very accurate rig positioning relative to the existing wells was critical for the success of the lift. ICON directed rig positioning operations.
Prior to the installation ICON assisted with the tie-back of four existing wells and installation of conductor guides. ICON directed all rig construction and mooring operations during the topsides installation phase.
The BKA PM3 lift was the heaviest jackup installation in SE Asia
The barge had no independent mooring system. Accurate barge positioning required carefully planned vessel operations. The complete topsides installation was carried out within a day.